Broadband Update- May 2018

Regional Update:
Installation of the 100 Gbps Transport Layer equipment has been completed in Grand Junction, Montrose, and Delta. Full IP configuration and testing continue over the next two weeks for full network integration. We are exploring potential CNL locations in Nucla and will complete transport layer equipment installation once a site has been obtained.

Gunnison and Ouray Counties:
Final design plans for the Carrier Neutral Locations in Ouray, Ridgway, Crested Butte and Gunnison are being completed. We expect to begin CNL buildout in June. We are exploring potential dark fiber access between Montrose and Ridgway.

Montrose County:
Construction is winding down to the anchor locations in Montrose County. Engineering for connectivity to Olathe is underway with DMEA and final plans for the CNL are being completed.

Delta County:
The IRU agreements between Region 10 and DMEA for the North Fork and has been completed. We will begin the installation testing and turn-up of the regional network in Cedaredge, Crawford, Hotchkiss, and Paonia the first part of June.

Region 10, Elevate Fiber and ClearNetworx have entered into agreements with for middle-mile fiber access in multiple areas to deliver service to multiple businesses in the city of Delta. These service offerings now available for select business locations throughout the city.